100k Construction Update - Week 5
Uploaded on Nov 10, 2008 / 1097 views / 16546 impressions / 0 comments
Description
After many delays SIPs are delivered, plumbing has been run, radiant was installed and the slab has been poured.
Hey! Postgreen is using Viddler for online video, and so can you!
Hide thisUploaded on Nov 10, 2008 / 1097 views / 16546 impressions / 0 comments
After many delays SIPs are delivered, plumbing has been run, radiant was installed and the slab has been poured.